By Matthew Nash

Olympic Peninsula News Group

CARLSBORG After more than a year under construction, the Carlsborg Sewer Project is wrapping up, Clallam County staff report.

Meggan Uecker, solid waste coordinator for Clallam County, said crews with contractor Pacific Civil and Infrastructure are striping the roads including Carlsborg Road and Business Park Loop, paving the pump station, rerouting the Olympic Discovery Trail and paving a portion of Hooker Road south of U.S. Highway 101.

About 85 sites, Uecker said, can begin connecting to the system starting this coming Wednesday.

They have until December to connect to the system, she said, but county staff are available to help people through the process. If residents do not finish their sewers by December, theyll have to renew their application and pay the current connection fee of $1,500.

Physical work on the $9.22 million project began in April last year and was deemed substantially complete prior to an April 1 deadline this year to obtain a 0.25 percent interest rate on the $10 million state Public Works Trust Fund loan.

The completion means water can travel through piping from the Carlsborg pump station to the city of Sequim via the Dungeness River Bridge over Highway 101 to a collection system at Grant Road and be sent to Sequims Water Reclamation Facility.

Uecker said staff members are holding off on saying just how well the project went because they are in the assessment process.

Were excited its done and ready to move into this phase [of completion], she said.

With the project nearly complete, Uecker said traveling should be easier following the cleanup and a new center turn lane being painted along Carlsborg Road.

With it being unmarked, people were complaining of other folks not knowing where to drive, she said.

Late last year, several Carlsborg businesses reported having a hard time with the construction detouring traffic away from the area, leading some to cut back on staff hours and days of operation.

Lisa Deese, owner of the Old Post Office Sweets & Gifts, 751 Carlsborg Road, said her business has been night and day and really close to not surviving.

It was so dead during the construction, but now Im going to have to kick it into high gear, she said.

Now that the construction is over, its been amazing. All of my customers are thrilled.

Val Culp, co-owner of the Old Mill Cafe, 721 Carlsborg Road, previously said it was one of the businesses to cut back on staff hours but its now returned to pre-construction operations.

Its definitely a lot better since the road was finished, she said. Now that its picked up, weve got our regular schedule again.

Michael Dew, owner/general manager of Pioneer Propane, 931 Carlsborg Road, said in the winter, construction made it difficult to get in and out of his business. However, his sales representative Stephanie Segle came up with the idea to introduce a loyalty card with which, after customers buy 50 gallons of propane in a canister for barbecues/RVs, theyll receive 5 gallons free.

Dew, who opened Pioneer Propane in 2009, said Segles idea helped his business stay proactive and the idea was a boost for the business.

Uecker said residents who signed up before March 31 paid $500 to connect to the sewer and those who sign up before April 1, 2019, will pay $1,500. Residents who sign up after that will pay $8,000.

A lot of sites can still connect, and with a change in zoning, many properties can subdivide, which may create more hookups, she said.

Carlsborg sewer customers will pay a $26 base rate per residential unit, and those with meters will pay $8.66 per 100 cubic feet of water used per month, with non-metered customers paying a flat monthly fee of $78.80 per unit.

County officials estimate the average sewer bill will be about $70.

Dew, whose business is right next to the pump station, said he was a supporter of the system early on and signed up when it first became available.

It worked for the Romans and it certainly can work for us, he said.

Culp said she and her husband, Larry, opted not to connect to the sewer because they spent $40,000 in June 2015 to install new septic tanks at the prompting of the Department of Health.

I cant see paying the [connection fee] and paying to decommission the tanks, she said.

Were going to ride it out.

If the Culps or any homeowners/business owners with functioning septic systems not connected to the sewer system were to sell, thed have to connect within a year. Newly constructed homes also must connect to the system within a year because new septic tanks are not allowed in the Carlsborg Urban Growth Area.

For more information on the project, contact Uecker at 360-417-2441 or muecker@co.clallam.wa.us, or visit http://www.clallam.net/PublicWorks/CarlsborgSewer.html.

________

Matthew Nash is a reporter with the Olympic Peninsula News Group, which is composed of Sound Publishing newspapers Peninsula Daily News, Sequim Gazette and Forks Forum. Reach him at mnash@sequimgazette.com.

A recently paved section of the Olympic Discovery Trail now loops around the Carlsborg Sewer Projects pump station north of Savannah and Village lanes. Its one of the final pieces for the project, which finishes this week. (Matthew Nash/Olympic Peninsula News Group)

Crews recently painted new lines on Carlsborg Road, including a center turn lane, following the completion of the Carlsborg Sewer Project. (Matthew Nash/Olympic Peninsula News Group)

See original here:
Crews finishing Carlsborg sewer project; residents can connect to system starting Wednesday - Peninsula Daily News

Related Posts
July 4, 2017 at 9:43 am by Mr HomeBuilder
Category: Sewer and Septic - Install