Tonawanda News Renovations on the Tonawanda Middle and High Schools music rooms could begin this week as part of the districts nearly $12 million endeavor, capital project managers told the school board at Tuesday nights regular meeting.

We met with the contractors at a kick-off meeting, but we havent received the contracts back yet, Gloria Ciminelli, of Pike Co., said. Once we get them, construction will begin.

Earlier in January, the board held a special meeting to approve the bids for the project to ensure construction began on time. The renovations were set to begin today, Ciminelli said.

The bids were very successful, we were under budget and it will allow us to start on time, she said.

The district originally planned to complete additions at the school for the two rooms, but the bids for that portion of the project came in more than $600,000 over budget.

The board then decided to renovate the two rooms instead of completing the expansion. The work will include raising the roof of the band room and expanding the width of the choral room to provide more space and better acoustics.

But change in plans meant the projects architectural firm, Wendel, had to go back to the drawing board and prepare an addendum for state Department of Education approval. The addition was initially set to be complete in November.

Once construction begins, the demolition of the choral room will take place first, and temporary enclosures will ensure the safety of students. Demolition of the band room will take place next.

When the weather breaks, in mid-March, well take the band room roof off. Thats a major part of this project, Ciminelli said.

The work will be complete by the end of June.