Originally constructed in 1978, Great River Energys high-voltage direct-current system is one of a few of its kind in the world and one of the electric generation and transmission cooperatives most valuable assets. The co-ops high-voltage direct-current (HVDC) system consists of a 436-mile (702-km) HVDC transmission line and two converter stations, one at each end of the line, that convert electricity from alternating-current (AC) power to direct-current (DC) power and vice versa. Nearly all the power is delivered from Coal Creek Station the co-ops largest power plant in Underwood, North Dakota, U.S., to Minnesota, where the utilitys 28 member co-ops are located.
After eight years of planning and preparation, Great River Energy recently upgraded the unique HVDC system, successfully completing one of the most significant transmission projects in its history. The utility and ABB the manufacturer of its HVDC system completed the upgrade from March 7, 2019, to May 17, 2019, during a power plant outage that was planned for regular maintenance. As part of the upgrade, all the equipment in the converter stations was replaced with todays technology. This included replacing the conversion equipment (valves), controls, cooling towers and smoothing reactors as well as updating the DC yards. All the work either took place inside or directly supporting the converter stations, not on the transmission line itself.
Although ABB has completed other similar HVDC system upgrades, this project was unique because the work had to be done in an extremely tight construction window. With only a 74-day power plant outage in which to work, Great River Energy carefully planned for years to ensure the work could be completed on time, on budget and safely.
Working Ahead
Great River Energy, ABB and its contractors developed a detailed schedule in Primavera, a project management software tool. The schedule captured every task that had to be completed during the outage, how long each task should take and the date by which each task should be completed. About 1350 tasks were identified for each of the two converter stations. The design of the schedule helped to make the critical-path elements clear to the contractors. Everyone knew what the priorities were to ensure resources were available and tasks completed safely and on time. This schedule had to be followed to the letter to ensure the outage went smoothly.
Knowing the construction window was tight and nonnegotiable, Great River Energy took every opportunity to ask what could be done ahead of the March 7 outage start date to eliminate tasks and ensure success. As a result, five major items were completed ahead of time.
First, a plan was put in place to ensure all major equipment was delivered and ready on-site prior to the start of the outage. To facilitate this, Great River Energy constructed a 35,000-sq ft (3251-sq m) permanent facility at the Coal Creek Station site in North Dakota and ABB constructed a temporary 20,000-sq ft (1858-sq m) facility at the Dickinson converter station in Minnesota. This enabled ABB to deliver all major equipment to the sites well before the start of the outage and preconstruct sections of the new valves in the winter of 2018.
Second, Great River Energy proactively worked with the Midwest Reliability Organization, the regional organization for the North American Electric Reliability Corporation (NERC), to discuss the co-ops plan for ensuring compliance. Great River Energy was one of the first utilities to complete a project of this nature since versions 5 and 6 of the Critical Infrastructure Protection (CIP) standards became mandatory. Great River Energy had to manage the compliance of both the old control systems and the new control systems while they were being installed and uninstalled before, during and after the outage. This included tracking more than 2000 cyber assets subject to NERC CIP requirements.
To help test compliance and the plan overall, in early 2019, the co-op and ABB replaced the controls on six AC filter banks. This also reduced the amount of equipment that would have to be commissioned during the 74-day outage.
Third, the floors of the converter station buildings were prepared to ensure they could withstand the weight of the cranes coming in and out of the buildings to demolish the old valve stacks. The floors of the old buildings were not designed for the weight of the cranes. If the floors collapsed during demolition, the impact would have been catastrophic.
To reinforce the converter station floors, ABB installed about an additional 60 braces and posts. The floors were covered with 1/2-inch to 3/4-inch (12.7-mm to 19-mm) thick steel plates. Weighing between 800 lb and 1000 lb (363 kg to 454 kg) each, the plates were hauled in by a forklift and put in place with magnets.
Fourth, in the spring of 2018, during a regularly planned maintenance outage, crews staged equipment, cut holes in the basement walls of the converter stations, and poured concrete for foundation piers, cooling towers and cable trench.
Fifth, to eliminate airborne particulates, Great River Energy hired contractors to prepare pipes that were coated in lead-based paint and had to be cut during demolition.
Demolition and Construction
The first day of the outage, March 7, was dedicated exclusively to environmental preparations Great River Energy staff had to make to ensure the work site was safe for contractors. Because the converter stations were built more than 40 years ago, a significant amount of hazardous material had to be addressed.
During the first 24 hours of the outage, Great River Energy contractors removed and disposed of 12,000 gal. (45,425 L) of glycol from the old air-cooled valves and 8600 gal. (32,555 L) of mineral oil used in the smoothing reactor. Certified contractors also removed non-friable asbestos from the heating ventilation and air conditioning ducts.
Great River Energys HVDC system is made up of two poles, which the co-op refers to as pole 1 and pole 2. The 74-day outage plan was designed for a 42-day outage of pole 1, a 35-day outage of pole 2 and an overlap of three days where both poles would not be operating.
On the second day of the outage, after a safety meeting, ABB immediately began demolition of pole 1 equipment, specifically on the fan room and valve hall. The task was much like gutting an old car; everything had to come out. In this case, it was like working simultaneously on two similar carsthat were 436 miles apart.
Coordination was a daily task for Great River Energy and ABB as work schedules continually were revised and communicated to ensure the more than 150 contractors knew what to do next at each site. The time devoted to developing the meticulous schedule paid off. The work closely followed the original plan, except for a few minor issues and some unwelcome weather. Crews in North Dakota worked in high winds and significantly below-average temperatures, and Minnesota got piles of snow. More than 100,000 cu yards (76,456 cu m) of snow had to be removed from the Dickinson station parking lots and the DC yard so that project work could continue.
Safety also was a key focus. Before each shift began, a safety meeting was held with all contractors to talk about what work had to be accomplished. Each contractor then had a tailgate meeting to discuss the specifics of the tasks.
Despite the challenges, by the end of the day March 12, the pole 1 valve halls at both the Dickinson and Coal Creek Station converter stations were empty, ahead of schedule. Crews transitioned from demolition to installation, with April 8 in mind. That was the day pole 1 had to be installed entirely, so commissioning could begin. To move to the next stage of the project, ABB had to demonstrate the pole 1 system was ready for operation.
Bi-Pole Outage
April 15 to April 17 were some of the most critical days of the outage because some of the work could only be completed with the system entirely out of service, and, during that time, Great River Energy would not be selling any power from Coal Creek Station into the market. In addition, this outage required coordination not only with the plant but also the regional transmission organization, the Mid-Continent Independent System Operator (MISO), and Blue Flint Ethanol, which relies on Coal Creek Station for steam.
During the bi-pole outage, the control systems that make the two poles work together had to be replaced and fully commissioned a large task to accomplish in just three days. The replacement was completed on schedule, but commissioning was delayed for one day because Great River Energy and ABB felt crews needed rest to ensure they could work safely.
After the bi-pole outage, on April 18, pole 1 was energized and the pole 2 outage continued. Crews repeated the same process for pole 2 they had followed for pole 1. On the first day, Great River Energy and its contractors removed hazardous waste. Next, they demolished the old valves and installed the new technology.
As expected, the process for demolishing and installing the equipment for pole 2 was more efficient because lessons had been learned from doing the work on pole 1. The outage time specified in the contract was reduced by seven days and ABB was able to cut the night shift one and a half weeks into the pole 2 outage. Ultimately, ABB completed the work and was ready for commissioning by May 13.
Fault Testing By Drones
Before the system could be placed in service, the protection system had to be tested as well as the line fault locator, to ensure it would locate the position of the fault correctly along the line. Great River Energy had researched various methods for staging faults to do the testing. Ultimately, the co-op chose to use an unmanned aircraft system (UAS) to carry a copper wire into the line, which caused the fault. Of the options available, using a UAS clearly proved to be the safest and most efficient.
Staged faults were performed on both poles, some near the Coal Creek Station converter station, some at the midpoint of the HVDC line and some close to the Dickinson converter station. A significant amount of preparation had to be done to ensure the fault testing process would follow Great River Energys technology use policy and comply with all U.S. Federal Aviation Administration rules and regulations. The co-ops line technicians were on-site with the fault testing team in case something unexpected happened and a repair was needed.
However, the most challenging part of the process was scheduling a fault because this required coordination with Coal Creek Station, both converter stations, MISO and the weather. The testing could not take place if winds were above 22 mph (35 kmph) or there was any precipitation. Ultimately, the schedule came together. Testing was performed over three days, May 15 to May 17, and generally went as expected.
Later in the afternoon on May 17, two days ahead of schedule, ABB cleared Great River Energy to proceed to commercial operation. Construction and testing were complete. The upgrade was finished.
The Results
Great River Energy successfully completed a major upgrade to its HVDC system on time and under budget, safely replacing all the equipment in two 40-year-old converter stations with todays advanced technology in a total of 72 days. Although many people contributed to the project, a core group of employees and partners including ABB, Teshmont Consultants LP and Michels Corp. ultimately overcame complex and unique challenges to make it happen.
There were unique safety and environmental considerations throughout the project, and communications was an ongoing challenge. People and equipment were located around the world in nine countries, bringing different cultural norms and time zones into play. Great River Energy employees spent a total of more than 900 days away from home, 350 of those overseas. At the peak of construction, approximately 150 contractors were working at each converter station site 24 hours a day, six days a week. In normal working conditions, only three employees would be at each site.
Great River Energys HVDC system already is delivering significant benefits. The amount of energy needed to operate the converter stations has been reduced dramatically. Additionally, while the old water-cooled valves used approximately 4 million gal. (15.1 million L) of water each month, the new air-cooled valves do not use any water.
In the end, the key success measure is continued world-class reliability. Great River Energys HVDC system has been one of the most reliable in the world over the last 40 years. Now, with todays advanced HVDC technology in place, the expectation is the co-op and its member-owners can look forward to another 40 years.
For more information:
ABB | http://www.abb.com
Blue Flint Ethanol | http://www.blueflintethanol.com
Michels Corp. | http://www.michels.us
Midwest Reliability Organization | http://www.mro.net
Mid-Continent Independent System Operator | http://www.misoenergy.org
Teshmont Consultants | http://www.teshmont.com
- Air Changes Heating & Cooling LLC Expands Services in the Philadelphia Area - openPR - September 29th, 2024 [September 29th, 2024]
- Northwest Plumbing, Heating & AC Offers Central Air Inspection and Furnace Services as Winter Approaches - GlobeNewswire - September 20th, 2024 [September 20th, 2024]
- Abundant Air Wins Build Construction & Engineering Award for Heating & Cooling Experts of the Year 2024 Winnipeg - The Globe and Mail - September 20th, 2024 [September 20th, 2024]
- Air conditioning repair operations inundated with calls as heat indexes rise - WLWT Cincinnati - June 24th, 2024 [June 24th, 2024]
- Hiller Plumbing, Heating, Cooling & Electrical Receives Ninth Consecutive Ruud Top Pro Partner Award - PHCPPros - June 24th, 2024 [June 24th, 2024]
- AC Repair Near Me: Top Air Conditioning Repair Services - The Jerusalem Post - January 22nd, 2024 [January 22nd, 2024]
- What to do if you lose heat during cold winter temps in Chicago area - NBC Chicago - January 22nd, 2024 [January 22nd, 2024]
- Ductless mini-split systems offer air conditioning for BC homes with boilers Surrey Now-Leader - Surrey Now Leader - December 28th, 2021 [December 28th, 2021]
- PJ MAC HVAC Service & Repair, a heating and air conditioning repair company, has launched a new location in Reading, PA - Virtual-Strategy... - August 11th, 2021 [August 11th, 2021]
- United MHC Offers the Best Heating and Cooling Equipment for Multi-Site Properties and Food and Beverage Industrial Facilities - Digital Journal - August 11th, 2021 [August 11th, 2021]
- Dillon's Heating & Cooling Shared the Causes of Hot and Cold Spots - Digital Journal - August 11th, 2021 [August 11th, 2021]
- Gary's Heating Service, Inc. Is a Leading Provider of HVAC Service in Lansing and Dewitt, Michigan - Digital Journal - August 11th, 2021 [August 11th, 2021]
- The Ancient Persian way to keep cool - BBC News - August 11th, 2021 [August 11th, 2021]
- Optimal Office Temperature: How to Get It and Why It Matters - Legal Reader - August 11th, 2021 [August 11th, 2021]
- J & J Services is Making Their Solutions Affordable To All - Press Release - Digital Journal - February 14th, 2021 [February 14th, 2021]
- San Diego AC Repair Company Lists the Impressive Numbers of Steps They Perform When Doing Air Conditioning Tune-Ups - Press Release - Digital Journal - February 14th, 2021 [February 14th, 2021]
- Furnace repair: Learn whom to call and when to call for furnace service in NY! - The Open News - February 5th, 2021 [February 5th, 2021]
- Greenwood-based service firm builds its own workforce - Indianapolis Business Journal - February 5th, 2021 [February 5th, 2021]
- Education and Transportation Front and Center in Capital Plan - Nashville.gov - February 5th, 2021 [February 5th, 2021]
- Air Care Cooling & Heating LLC the Bastion of Comfort and Peace of Mind gives Free APCO UV Lights. - Press Release - Digital Journal - February 5th, 2021 [February 5th, 2021]
- Young Entrepreneur | The Business Journal of greater Keene, Peterborough and Brattleboro | sentinelsource.com - The Keene Sentinel - February 5th, 2021 [February 5th, 2021]
- Dominion Energy offers bill saving tips during cold weather months - WCBD News 2 - February 5th, 2021 [February 5th, 2021]
- San Diego CA Heating and Air Conditioning Service Discusses Less Obvious Signs that Indicate an AC Repair is Needed - Press Release - Digital Journal - January 27th, 2021 [January 27th, 2021]
- Heating company Pays It Forward to family of man in hospice - Fox17 - January 27th, 2021 [January 27th, 2021]
- HVAC Contractors Look at Weather Forecasts and Prepare for Winter - ACHR NEWS - October 20th, 2020 [October 20th, 2020]
- Giving Back to the Community - Patch.com - October 20th, 2020 [October 20th, 2020]
- Plumb Works Inc Receives the 2020 'Safety First!' PHCC Contractor of the Year Award - PR Web - October 20th, 2020 [October 20th, 2020]
- LENNOX INTERNATIONAL : Management's Discussion and Analysis of Financial Condition and Results of Operations (form 10-Q) - marketscreener.com - October 20th, 2020 [October 20th, 2020]
- Larrupin Cafe on INSPECTED! Humboldt County Health Inspections from the Lost Coast Outpost - Lost Coast Outpost - October 20th, 2020 [October 20th, 2020]
- Why a Home Inspection is must before buying homes in Delhi - Siliconindia.com - October 20th, 2020 [October 20th, 2020]
- Education Beat: Northwestern needs $4 million in upgrades; where will junior high students go? - East Village Magazine - June 28th, 2020 [June 28th, 2020]
- Aluminum or Steel Mold: Whats the Right Fit for Your Product? - TippNews DAILY - June 28th, 2020 [June 28th, 2020]
- PHCC Connect event will be virtual show - Contracting Business - June 28th, 2020 [June 28th, 2020]
- Heat Interface Units Market(Covid 19 Impact) 2020 Worldwide Industry Size, Key Vendors, Growth Drivers, Opportunity And Competitive Landscape Forecast... - June 28th, 2020 [June 28th, 2020]
- LOCKWOOD: Some things to know about preventive home maintenance - Mcalester News Capital - June 6th, 2020 [June 6th, 2020]
- Coolray Partners with DGM Racing and Josh Williams for Atlanta Race Weekend - Collision Repair Magazine - June 6th, 2020 [June 6th, 2020]
- Petri Plumbing & Heating offers HVAC advice to owners of older homes as temperatures rise - PRNewswire - June 6th, 2020 [June 6th, 2020]
- Energy Efficient AC Repair and Installation Updated for Lafayette, LA - Yahoo Finance - May 22nd, 2020 [May 22nd, 2020]
- Homeowners Should Get Their Air Conditioning Units Ready for Summer - Press Release - Digital Journal - May 22nd, 2020 [May 22nd, 2020]
- Plumbers, Trusted Plumbing & Heating, in Renton WA Continue to Earn Customers' Trust Amidst COVID 19 - MENAFN.COM - May 22nd, 2020 [May 22nd, 2020]
- It's Okay To Be Comfortable At Home All Year Long - Press Release - Digital Journal - May 22nd, 2020 [May 22nd, 2020]
- County leaders can't escape reality that current jail on West Main Street may need costly repairs - The Batavian - May 22nd, 2020 [May 22nd, 2020]
- $6.6 Bn Underfloor Heating Market by Offering, Subsystem, System Type, Application, Component, Installation Type and Region - Global Forecast to 2025... - May 22nd, 2020 [May 22nd, 2020]
- Covid 19 Pandemic | Heat Interface Units Market 2020 Business Strategies, Product Sales and Growth Rate, Assessment to 2025 - Cole of Duty - May 22nd, 2020 [May 22nd, 2020]
- HomeServe to help with DIY repair projects through new 'Telefix' - News 12 Bronx - May 10th, 2020 [May 10th, 2020]
- Practical steps that will help keep your home COVID-19 free - Magnoliareporter - May 10th, 2020 [May 10th, 2020]
- Hiller Taking Every Step Possible to Minimize the Impact of COVID-19 - Press Release - Digital Journal - May 10th, 2020 [May 10th, 2020]
- Gates Industrial (NYSE:GTES) & Ingersoll-Rand (NYSE:IR) Head to Head Analysis - Redmond Register - March 24th, 2020 [March 24th, 2020]
- ANGI Homeservices Asks Congress to Provide Relief and Protection Directly to America's Local Home Services Professionals Amid the COVID-19 Pandemic -... - March 24th, 2020 [March 24th, 2020]
- EZ Comfort Air Conditioning & Heating Announces Financing Options for AC Repair in The Woodlands, TX - Benzinga - March 9th, 2020 [March 9th, 2020]
- NJ HVAC Services by Cardwell Reports That Neighbors Are Switching To Cardwell At An Incredible Rate More Than Any Other Heating and Air Conditioning... - March 9th, 2020 [March 9th, 2020]
- Everett compiles $150 million list of repair over 20 years - The Columbian - March 9th, 2020 [March 9th, 2020]
- Atascadero Heater Repair Company Releases The Top Ways To Know When It's Time To Replace The Old HVAC - PR Web - March 9th, 2020 [March 9th, 2020]
- High tech in the basement at university greenhouse - hortidaily.com - March 9th, 2020 [March 9th, 2020]
- Largo FL Air Conditioning Repair HVAC And Air Conditioner Installation Launched - Newswire - March 2nd, 2020 [March 2nd, 2020]
- How Much Will Repairs and Upgrades Cost? Get the Answers - RisMedia.com - March 2nd, 2020 [March 2nd, 2020]
- Army requests millions to fix homes for high-ranking officers in the Washington area - Stars and Stripes - March 2nd, 2020 [March 2nd, 2020]
- Geothermal - SWM Will Take Over Technical Operational Management Of Geothermal Power Plant In Bruck - Renewable Energy Magazine - February 21st, 2020 [February 21st, 2020]
- CCAR shares threats, precautions for working on hybrid, fully-electric cars - Repairer Driven News - February 21st, 2020 [February 21st, 2020]
- Crowley TX HVAC Repair and Installation Heating and Cooling Services Launched - Newswire - January 13th, 2020 [January 13th, 2020]
- Nailing It Down: Singing the praises of ductless heat pumps - The Daily World - January 13th, 2020 [January 13th, 2020]
- How A Climate Change Nonprofit Got Eversource Thinking About A Geothermal Future - WBUR - January 13th, 2020 [January 13th, 2020]
- Winsupply Acquires Rosen Supply, Plumbing and Heating Distributor - ACHR NEWS - January 13th, 2020 [January 13th, 2020]
- Midland business celebrates 40 years - Midland Daily News - December 5th, 2019 [December 5th, 2019]
- Waste heat reuse and CO2-neutral energy supply concept among winners of German energy efficiency awards - Envirotec - December 5th, 2019 [December 5th, 2019]
- Heating and Air Conditioning Repair - Service Champions - May 29th, 2019 [May 29th, 2019]
- AC Repair Fort Smith - HVAC Heating & Cooling Services - May 4th, 2019 [May 4th, 2019]
- AC Repair Clermont, FL & Doctor Phillips, FL, Heating ... - April 21st, 2019 [April 21st, 2019]
- Valley Air Repair The heating & cooling experts - April 21st, 2019 [April 21st, 2019]
- M&M Heating and Cooling - Air Conditioning Repair Ohio ... - March 27th, 2019 [March 27th, 2019]
- Affordable Heating and Cooling | Service, Repair | Windsor ... - March 27th, 2019 [March 27th, 2019]
- Superior Heating and Ventilating, Inc | Home - March 6th, 2019 [March 6th, 2019]
- AC Maintenance, Heating & Cooling, Air Conditioning Repair ... - January 31st, 2019 [January 31st, 2019]
- North Shore Heating and Cooling - Furnace Repair Service ... - January 31st, 2019 [January 31st, 2019]
- Furnace Repair Service Chanhassen MN | Peak Heating ... - January 12th, 2019 [January 12th, 2019]
- Right Now Heating & Air Conditioning - September 21st, 2018 [September 21st, 2018]
- Atlantic Heating & Cooling AC/Heating Repair ... - August 17th, 2018 [August 17th, 2018]
- The 10 Best Air Conditioning Companies Near Me (with Free ... - August 7th, 2018 [August 7th, 2018]
- HVAC/Air Conditioner Repair Services - July 24th, 2018 [July 24th, 2018]
- Edison Heating & Cooling: Residential and Commercial HVAC ... - July 24th, 2018 [July 24th, 2018]