Anderson CountyPalestine Maintenance is scheduled to perform edge repair on FM 837. Expect lane closures with flaggers and a pilot car managing traffic control.

Anderson County construction projects updates:

US 79 Super 2 Project

The contractor is scheduled to continue work on roadway elements. The speed limit has been reduced to 60 mph throughout the project limits. Motorists should use caution when traveling through the project and expect lane closures and delays. Project consists of widening for a Super 2, including sub-grade work, surface treatment, base and surface hot mix asphalt, widening structures, bridge rail, MBGF, signage and permanent striping.

----------------------------------------

Cherokee CountyJacksonville maintenance crews are scheduled to begin edging on FM 2750 between FM 2064 and SH 110. Expect daytime lane closures with traffic controlled by flaggers. Rusk Maintenance crews will be working on base repair and edges on FM 851. Expect daytime lane closures.

Cherokee County construction projects updates:

FM 22 Safety Widening and Bridge Replacement Project

The contractor is scheduled to continue widening the roadway and begin construction on the bridge at Little Turnpike Creek. Flaggers will be present during construction hours. Expect daily lane closures when work is being done. The bridge will be closed during construction. The project will widen the existing roadway, replace three bridges and incorporate safety upgrades.

US 84 Widening

The contractor is scheduled to continue widening cross structures, driveway upgrades and begin base repairs/widening. Lane closures will be in place. Expect delays on this corridor when construction is in progress. The project will widen and resurface the roadway, along with adding safety upgrades.

FM 235 Safety Widening

No work is scheduled this week. No lane closures will be in place. The project widens the existing roadway and incorporates safety upgrades.

County Road Bridge Replacement Project

No work is scheduled on CR 3203 and CR 1504. Both roadways are open to traffic. Construction of the new bridges is ongoing on CR 2905 and CR 2614. Both roads are closed to through traffic. The project is replacing the existing bridges at each location with new structures.

SH 204 Super-2 Widening Project

The contractor is scheduled to continue placing mowstrip and final surface striping. Lane closures will be in place during construction. The project adds passing lanes and incorporates safety upgrades.

US 69 Sidewalks in Jacksonville

No work is scheduled. The project is constructing sidewalks along US 69 in Jacksonville.

US 79 Rehabilitation Project

The contractor is awaiting final punch list. Lane closures will be in place, expect delays on this corridor when construction is in progress. The work zone speed limit is 60 mph. The project will rebuild the roadway pavement and upgrade bridge rails.

SH 21 Resurfacing Project

The contractor is scheduled to begin road work construction on driveway upgrades and structure extensions. Lane closures will be in place. The project will consist of pavement resurfacing.

----------------------------------------

Gregg CountyMaintenance crews will continue bridge channel maintenance on SH 135, just north of SH 31. There will be possible right-lane closures north or southbound over Rabbit Creek and Rabbit Creek Relief bridges. Flaggers will be present if needed. Crews also plan to continue with mobile operations, patching potholes and removing debris from various roadways. Mobile operations will have contract TMAs present for protection.

Gregg County construction projects updates:

This project is part of the City of Longview Guthrie Creek Trail project. It will consist of building a bridge over Guthrie Creek to allow bicyclist and pedestrians to travel under Spur 63. The traffic will be reduced to two lanes, one northbound lane and one south bound lane to allow the contractor to build half of the bridge. Traffic will be switched later to allow completion of the bridge construction. Expect delays.

FM 2204, etc., Safety Improvement Project

Contractor is scheduled to complete punch list items this week. This project consists of culverts, safety end treatments, drainage upgrades, new MBGF and driveway asphalt. There will be daytime lane closures. Expect delays.

FM 2206/Harrison Road

This project consists of widening a two-lane road to four lanes with a center turn lane. This includes drainage structures, flexible base, curb and gutter, sidewalks, hot mix and pavement markings. Contractor will be extending culverts and constructing detours. There will be daytime lane closures. Expect delays.

FM 2206/Harrison Road

This project consists of widening a two-lane road to four lanes with a center turn lane. This includes drainage structures, new bridge, flexible base, hot mix and pavement markings. Contractor will be extending culverts and constructing detours. There will be daytime lane closures. Expect delays.

----------------------------------------

Henderson CountyAthens maintenance is scheduled to perform base work on SH 198 between SH 31W and FM 1214. Expect delays with flaggers controlling traffic.

Henderson County construction projects updates:

SH 198 Bridge Project

The contractor is scheduled to work on the new northbound bridge and roadway elements. Motorists should be prepared for lane closures and delays. The speed limit has been reduced to 50 mph throughout the project. The project consists of the construction of replacing bridges, approaches, grading, structures, asphalt concrete pavement (ACP) base, ACP surface, retaining walls, curb & gutter, MBGF, and pavement markings.

SH 334 Bridge Project

The contractor is scheduled to continue final cleanup work. Expect lane closures and delays. The project will upgrade the roadway from two to four lanes. The contract consists of the construction of bridges, storm sewer, guardrail, base, pavement surfaces, and pavement markings.

----------------------------------------

Rusk CountyMaintenance crews are scheduled to begin edge repairs on FM 839 near Lake Striker. Flaggers will control traffic with one-way traffic setups in all locations. Expect daytime lane closures.

----------------------------------------

Smith CountyTyler Maintenance will be performing ditch work on FM 2493 (Old Jacksonville Hwy) near Loop 323. Expect daily lane closures with flaggers controlling traffic. A second crew will be on SH 155 south, just before the first bridge at Lake Palestine. This crew will also be performing ditch work off the road in the right-of-way. Once this job is complete, this crew will move to FM 346 in Flint to extend a culvert under the roadway just before FM 2868. This will be under lane closures with flaggers controlling traffic. This area is expected to see heavy congestion. Please seek an alternate route.

Smith County construction projects updates:

US 271 Rehab, Turn Lanes, and Pavement Overlay

Crews will be installing driveway culverts on the northbound and southbound sides. Traffic control will be managed by flaggers as needed. The project consists of paving, structures, MBGF, and pavement markings from I-20 north to the Gregg County line. The portion from I-20 to FM 16 also includes turn lanes and pavement rehabilitation.

FM 2493 Widening Project

The contractor is scheduled for miscellaneous project clean up. Temporary lane closures are anticipated from 9 am to 4 pm. The project will widen FM 2493 from two lanes to a four-lane divided roadway with a flush median.

US 69 Overpass at FM 346

Contractor is scheduled to complete punch list items and project cleanup. Temporary lane closures will be in place for restriping and asphalt repair. The work zone speed limit is 60 mph on US 69. The project consists of building a new US 69 bridge over FM 346.

SH 155 Resurfacing Project

The contractor is scheduled to continue the mill and inlay between Frankston and Coffee City. Expect lane closures when work is in progress. When in progress, hours will be from 8 p.m. to 5 a.m., Sunday through Thursday nights. Expect delays. The project will resurface the roadway, upgrade drainage structures, and repair bridge joints.

Sidewalks at various locations in Smith County

The contractor is scheduled to continue work on SH 110 in Troup. Daily lane closures are expected. The project is adding sidewalks along SH 64W in Tyler, SH 110W, and SH 135N in Troup.

SH 135 Widening Project

No work is scheduled. The work zone speed limit is 45 mph. The project is adding passing lanes, improving drainage structures, and pavement resurfacing.

US 69 (Glenwood Blvd.) Resurfacing Project in Tyler

No work is scheduled. When in progress, work will be conducted from 8 p.m. to 5 a.m., Sunday through Thursday nights. The project consists of pavement resurfacing.

FM 344, etc., Safety Improvements

No work is scheduled. The project consists of improving drainage, culvert work, and guardrail upgrades.

US 69 (Broadway Ave.) Resurfacing Project

No work is scheduled. When in progress, work is slated from 8 p.m. to 6 a.m., Monday through Thursday, and on Sunday from 9 p.m. to 6 a.m. The project consists of bridge rail and pavement resurfacing.

I-20 Resurfacing Project

No work is scheduled. When work is in progress, the schedule is from 8 p.m. to 6 a.m., Sunday through Thursday. The work zone speed limit is 65 mph. The project consists of ramp improvements and frontage road construction.

SH 64 Bridge Maintenance

The contractor is scheduled to continue working on bridge repairs. When work is in progress, hours will be 9 a.m. to 4 p.m. Lane closures will be in place when working on the metal beam guard fence and retrofit rail. The project consists of bridge maintenance and repair.

Tyler State Park Bridge and Resurfacing Project

No work is scheduled for this project. The project will consist of bridge and pavement resurfacing.

I-20 Upgrades at Barber Road

This project consists of widening on ramps and exit ramps, culverts, drainage upgrades, new MBGF and bridge rails on the Barber Road overpass, and asphalt overlay. No work planned this week.

SH 110 & FM 346 Landscape Project

The contractor is scheduled to continue forming various landscape development. The project consists of landscape development.

Sign Replacement at Various Locations in Smith County

No work is scheduled this week. The project will consist of replacing small roadside signs.

----------------------------------------

Van Zandt CountyCanton Maintenance will be conducting base work on FM 316. Daytime lane closures will be in place with flaggers controlling traffic. Bridge crews will also be working in various locations in the county. No delays are expected.

Van Zandt County construction projects updates:

I-20 MBGF Improvements (Van Zandt, Smith, and Gregg counties)

Crews will be performing bridge rail work (eastbound side), concrete work, cleaning, and grading along the eastbound and westbound shoulders Gregg County (eastbound side), and cleaning and grading in Smith county (eastbound and westbound). Lane closures will be in effect nightly and will be managed by message boards and channelizing devices. This project is to construct safety improvements consisting of upgrading MBGF and mow strip.

SH 19 Super Two Widening & Overlay

Crews will be performing roadway widening operations on the southbound side and extending drainage structures on the northbound side. Traffic control will consist of a southbound shoulder closure and will be managed by flaggers as needed. The project consists of Super 2 work including grading, base repair, treated subgrade, flex base, OCST, PFC surface, structures, signs and pavement markings.

CR 2918, etc. Bridge Replacements

Crews will be installing concrete mowstrip on CR 2318 and CR 2918. Both roads remain closed on each side of the bridges until project completion. The project consists of removing and replacing four bridges.

Safety Improvement Project

The contractor is scheduled to continue driveways and drainage structures work on FM 346 in Smith County. Motorists should be prepared for lane closures and delays. The project includes grading, structure work, guard rail replacement, and bridge rail upgrades.

----------------------------------------

Wood CountyMaintenance crews will be performing bridge maintenance on US 69 at the Sabine River bridge. Expect one lane closure with flaggers and a pilot car. No delays are expected. Another crew will be on FM 14 between SH 154 and the Hawkins city limit performing base failure repairs. Expect one lane closure and a pilot vehicle and flaggers controlling traffic.

Wood County construction projects updates:

SH 154 Turn Lane Project

The project is substantially complete and in the punch-list phase. Shoulder closures could occur occasionally with minimal delay to motorists. The project includes pavement widening, hot mix asphalt concrete overlay, signs, and pavement markings.

----------------------------------------

I-20 Total Maintenance Contract

Go here to see the original:
TxDOT Project Updates for the Week of Jan. 24, 2022 - Texas Department of Transportation

Related Posts
January 25, 2022 at 5:35 am by Mr HomeBuilder
Category: Driveway Paving