Smyrna Town Council approved 5-1 Monday to move forward with Fearn Clendaniel as the architects for the Smyrna Police Station expansion.

Councilwoman Valerie White voted against the motion. Councilman Jeff Flairty couldn't make the meeting.

The approval came after a presentation from the project's construction manager Ed Ide, of i3a, and Wade Clendaniel, of Fearn Clendaniel Architects, on the changes made to the project.

In the presentation, Ide informed council that the parties involved i3a, Fearn Clendaniel, and the Police Building Committee were able to cut the price from $4.9 million to $3.8 million as council asked.

"We looked at the project from a number of different ways to bring the building down to match the budget," Ide said. "Holistically we looked at the square footages and rooms that can be eliminated at this point."

The group came up with two alternatives to cut. The first alternate is the tactical training room and storage area in the basement. The second alternate is to remove the large security area currently in the feasibility study.

"We plan on keeping them as alternates as time goes on, and if the budget shows that we can bring them back into the project and award those on bid day we will do that," Ide said.

By cutting space from these two alternates out of the basement, the committee was able to save about $463,000. Other cuts made include geothermal energy, LED lights, fixtures, furniture, equipment, and soft costs. In total, about $1.134 million was cut to bring the total price of the project down to $3.76 million just under the $3.8 million cap set by council. The $3.76 million includes a $300,000 contingency that was required from council.

Ide said the next steps in the process would be to hire an architect and then continue on with the design process and complete the schematic design phase, which would be to refine the preliminary layout. The steps after completing the design phase will be to evaluate the alternates, evaluate the energy, evaluate the building material, and to continue to work with the committee in terms of getting grants.

Overall, Ide said there are five levels of design: a feasibility study, schematic design, design development, a construction document, and then bidding.

See the rest here:
Smyrna Council approves architects for police station project

Related Posts
November 22, 2012 at 3:43 am by Mr HomeBuilder
Category: Architects