The City of Boise is working on several projects on Warm Springs Avenue that will cause travel delays.

The project has already begun and closures will cause traffic delays especially for summer concerts at the Idaho Botanical Garden.

The work will be done over three phases during a six-month period.

PHASE 1 - Pioneer Cemetery to Adams Elementary (Varying lane restrictions and detours)Scheduled Construction Timeframe: July 18, 2014 to October 24, 2014 Contractor: Titan Technologies Onsite Inspector: Kelly Lane; Phone: 440 - 4709

General Information: Warm Springs Avenue will be closed at Straughan Avenue from July 18th through July 23rd. Traffic will be detoured around the construction. Following this closure, Warm Springs Avenue will be reopened and there will continue to be lane shifts throughout the duration of the project. Drivers are advised to use caution while traveling through construction zone areas. The Trolley House restaurant, M&W Grocery, and Chevron gas station will remain open during construction.

PHASE 2 - Walling Drive to Warm Springs Golf Course (Full road closure)Scheduled Construction Timeframe: July 14, 2014 to August 22, 2014 Contractor: Titan Technologies Onsite Inspector: Kelly Lane; Phone: 440 - 4709

General Information: Construction will begin at E. Walling Drive and progress east along Warm Spring Avenue. The entire road segment will be closed during construction.

Please note: On July 17 and August 6 only, the road will temporarily open to accommodate traffic for the Outlaw Field Summer Concert Series held at the Idaho Botanical Garden. Flaggers will be onsite to direct traffic. The road will reclose after each concert. Please use caution when traveling through the construction zone area.

PHASE 3 - Warm Springs Golf Course to Starview Drive (Full road closure)*Scheduled Construction Timeframe: Mid-September 2014 - Mid November 2014 *NOTE: Entire stretch of road will not be closed at once during this phase.

General Information: More information will be available as it gets closer to the scheduled construction date.

See the original post here:
TRAFFIC ALERT: Warm Springs construction will last for six months